Therefore I had to find a way to show the project calendar in the Gantt chart and not the default one. As I had to print the Gantt chart and present to project sponsors, I knew that it would confuse them if they notice the non-working days in the bar chart. in Gantt chart only non-working days of the default calendar were shaded (weekends) and not all other specific non-working days of the project calendar (for example Easter holidays were not shown as non-working time). The project has specific non-working days in addition to weekends (Saturdays and Sundays).Īlthough calculations for start and finish times of activities were correct and consistent with the project calendar but what I saw in the Gantt chart area was totally different. Yesterday I was working on a project schedule model in P6 which its calendar was different with the default calendar of P6.
0 Comments